Rainier Square
Building
Completed
2020
Residential / Office
Concrete-Steel Composite
Tracking LEED
258.2 m / 847 ft
58
7
189
1000
31
102,193 m² / 1,099,996 ft²
You must be a CTBUH Member to view this resource.
You must be a CTBUH Member to view this resource.
Proposed
Construction Start
Completed
Usually involved in the front end design, with a "typical" condition being that of a leadership role through either Schematic Design or Design Development, and then a monitoring role through the CD and CA phases.
The Design Engineer is usually involved in the front end design, typically taking the leadership role in the Schematic Design and Design Development, and then a monitoring role through the CD and CA phases.
The main contractor is the supervisory contractor of all construction work on a project, management of sub-contractors and vendors, etc. May be referred to as "Construction Manager," however, for consistency CTBUH uses the term "Main Contractor" exclusively.
Other Consultant refers to other organizations which provided significant consultation services for a building project (e.g. wind consultants, environmental consultants, fire and life safety consultants, etc).
Material Supplier refers to organizations which supplied significant systems/materials for a building project (e.g. elevator suppliers, facade suppliers, etc).
You must be a CTBUH Member to view this resource.
Usually involved in the front end design, with a "typical" condition being that of a leadership role through either Schematic Design or Design Development, and then a monitoring role through the CD and CA phases.
The Design Engineer is usually involved in the front end design, typically taking the leadership role in the Schematic Design and Design Development, and then a monitoring role through the CD and CA phases.
The Design Engineer is usually involved in the front end design, typically taking the leadership role in the Schematic Design and Design Development, and then a monitoring role through the CD and CA phases.
The main contractor is the supervisory contractor of all construction work on a project, management of sub-contractors and vendors, etc. May be referred to as "Construction Manager," however, for consistency CTBUH uses the term "Main Contractor" exclusively.
Other Consultant refers to other organizations which provided significant consultation services for a building project (e.g. wind consultants, environmental consultants, fire and life safety consultants, etc).
Material Supplier refers to organizations which supplied significant systems/materials for a building project (e.g. elevator suppliers, facade suppliers, etc).
2022 CTBUH Awards
2022 CTBUH Awards
2021 CTBUH Awards
7 November 2019 - Event
29 October 2015 - Event
11 October 2021
CTBUH Journal 2022 Issue III
As the first in-person CTBUH International Conference after the Covid-19 shutdowns in 2020, the 2022 program contains an exuberant and exciting roster of presenters and...
21 September 2021
The Residences at Rainier Square have started welcoming their first occupants as of this summer. Located in downtown Seattle, the mixed-use project from Wright Runstad...
2022 CTBUH Awards
2022 CTBUH Awards
2021 CTBUH Awards
2022 CTBUH Awards
21 September 2021
The Residences at Rainier Square have started welcoming their first occupants as of this summer. Located in downtown Seattle, the mixed-use project from Wright Runstad...
21 August 2019
With construction topping off, Rainier Square is set to become the second-tallest skyscraper in the city of Seattle. The last steel beam was placed on...
05 April 2019
In yet another sign that Amazon is cooling on its hometown of Seattle, the retail-entertainment-tech giant says it is planning to move its entire...
04 March 2019
Long Island City isn’t the only place that Amazon is pulling out of. The tech giant made waves when it threatened to withdraw from its...
7 November 2019
The CTBUH Seattle Chapter hosts its annual fall workshop, discussing upcoming building code updates and urban planning for density.
30 October 2015
CTBUH 2015 delegates toured Seattle, gateway to Asia and icon of the Pacific Northwest, where they witnessed a showcase of tall building and technological innovation.
Subscribe below to receive periodic updates from CTBUH on the latest Tall Building and Urban news and CTBUH initiatives, including our monthly newsletter. Fields with a red asterisk (*) next to them are required.