547
Global
Height rank

Grand Lisboa

Macau
Height 258 m / 846 ft
Floors 48
Official Name
The current legal building name.

Grand Lisboa

Type
CTBUH collects data on two major types of tall structures: 'Buildings' and 'Telecommunications / Observation Towers.' A 'Building' is a structure where at least 50% of the height is occupied by usable floor area. A 'Telecommunications / Observation Tower' is a structure where less than 50% of the structure's height is occupied by usable floor area. Only 'Buildings' are eligible for the CTBUH 'Tallest Buildings' lists.

Building

Status
Completed
Architecturally Topped Out
Structurally Topped Out
Under Construction
Proposed
On Hold
Never Completed
Vision
Competition Entry
Canceled
Proposed Renovation
Under Renovation
Renovated
Under Demolition
Demolished

Completed

Completion

2008

Country
The CTBUH follows the United Nations's definition of Country, and thus uses the lists and codes established by that organization.

China

City
The CTBUH follows the United Nations's definition of City, and thus uses the lists and codes established by that organization.

Macau

Function
A single-function tall building is defined as one where 85% or more of its usable floor area is dedicated to a single usage. Thus a building with 90% office floor area would be said to be an "office" building, irrespective of other minor functions it may also contain.

A mixed-use tall building contains two or more functions (or uses), where each of the functions occupy a significant proportion of the tower's total space. Support areas such as car parks and mechanical plant space do not constitute mixed-use functions. Functions are denoted on CTBUH "Tallest Building" lists in descending order, e.g., "hotel/office" indicates hotel function above office function.

Hotel / Casino

Structural Material
All-Steel
Both the main vertical/lateral structural elements and the floor spanning systems are constructed from steel. Note that a building of steel construction with a floor system of concrete planks or concrete slab on top of steel beams is still considered an “all-steel” structure as the concrete elements are not acting as the primary structure.

All-Concrete
Both the main vertical/lateral structural elements and the floor spanning systems are constructed from concrete which has been cast in place and utilizes steel reinforcement bars and/or steel reinforced concrete which has been precast as individual components and assembled together on-site.

All-Timber
Both the main vertical/lateral structural elements and the floor spanning systems are constructed from timber. An all-timber structure may include the use of localized non-timber connections between timber elements. Note that a building of timber construction with a floor system of concrete planks or concrete slab on top of timber beams is still considered an “all-timber” structure as the concrete elements are not acting as the primary structure.

Mixed-Structure
Utilizes distinct systems (e.g. all-steel, all-concrete, all-timber), one on top of the other. For example, a Steel Over Concrete indicates an all-steel structural system located on top of an all-concrete structural system, with the opposite true of Concrete Over Steel.

Composite
A combination of materials (e.g. steel, concrete, timber) are used together in the main structural elements. Examples include buildings which utilize: steel columns with a floor system of reinforced concrete beams; a steel frame system with a concrete core; concrete-encased steel columns; concrete-filled steel tubes; etc. Where known, the CTBUH database breaks out the materials used within a composite building’s primary structural elements.

Steel Over Concrete

Height
Architectural
Height is measured from the level of the lowest, significant, open-air, pedestrian entrance to the architectural top of the building, including spires, but not including antennae, signage, flag poles or other functional-technical equipment. This measurement is the most widely utilized and is employed to define the Council on Tall Buildings and Urban Habitat (CTBUH) rankings of the "World's Tallest Buildings."

258 m / 846 ft

To Tip
Height is measured from the level of the lowest, significant, open-air, pedestrian entrance to the highest point of the building, irrespective of material or function of the highest element (i.e., including antennae, flagpoles, signage and other functional-technical equipment).
258 m / 846 ft
Occupied
Height is measured from the level of the lowest, significant, open-air, pedestrian entrance to the highest occupied floor within the building.
197.7 m / 649 ft
Floors Above Ground
The number of floors above ground should include the ground floor level and be the number of main floors above ground, including any significant mezzanine floors and major mechanical plant floors. Mechanical mezzanines should not be included if they have a significantly smaller floor area than the major floors below. Similarly, mechanical penthouses or plant rooms protruding above the general roof area should not be counted. Note: CTBUH floor counts may differ from published accounts, as it is common in some regions of the world for certain floor levels not to be included (e.g., the level 4, 14, 24, etc. in Hong Kong).

48

Floors Below Ground
The number of floors below ground should include all major floors located below the ground floor level.

4

# of Hotel Rooms
Number of Hotel Rooms refers to the total number of hotel rooms contained within a particular building.

433

# of Parking Spaces
Number of Parking Spaces refers to the total number of car parking spaces contained within a particular building.

338

Structural Material Steel Over Concrete
Structural Details:
Bottom of Building
Core
Reinforced Concrete
Columns
Reinforced Concrete
Floor Spanning
Reinforced Concrete Floorplate
Top of Building
Columns
Steel
Floor Spanning
Steel Beam

Rankings

#
547
Tallest in the World
#
335
Tallest in Asia
#
1
Tallest in Macau

Construction Schedule

2003

Construction Start

2008

Completed

Structural Engineer
Design

The Design Engineer is usually involved in the front end design, typically taking the leadership role in the Schematic Design and Design Development, and then a monitoring role through the CD and CA phases.

MEP Engineer
Design

The Design Engineer is usually involved in the front end design, typically taking the leadership role in the Schematic Design and Design Development, and then a monitoring role through the CD and CA phases.

Other Consultant

Other Consultant refers to other organizations which provided significant consultation services for a building project (e.g. wind consultants, environmental consultants, fire and life safety consultants, etc).

Façade

These are firms that consult on the design of a building's façade. May often be referred to as "Cladding," "Envelope," "Exterior Wall," or "Curtain Wall" Consultant, however, for consistency CTBUH uses the term "Façade Consultant" exclusively.

Material Supplier

Material Supplier refers to organizations which supplied significant systems/materials for a building project (e.g. elevator suppliers, facade suppliers, etc).

Façade Maintenance Equipment
Developer
Societe Jorges de Macau
Architect
Design

Usually involved in the front end design, with a "typical" condition being that of a leadership role through either Schematic Design or Design Development, and then a monitoring role through the CD and CA phases.

Dennis Lau & Ng Chun Man Architects & Engineers (HK) Ltd. (DLN)
Structural Engineer
Design

The Design Engineer is usually involved in the front end design, typically taking the leadership role in the Schematic Design and Design Development, and then a monitoring role through the CD and CA phases.

MEP Engineer
Design

The Design Engineer is usually involved in the front end design, typically taking the leadership role in the Schematic Design and Design Development, and then a monitoring role through the CD and CA phases.

Contractor
Main Contractor

The main contractor is the supervisory contractor of all construction work on a project, management of sub-contractors and vendors, etc. May be referred to as "Construction Manager," however, for consistency CTBUH uses the term "Main Contractor" exclusively.

Hip Hing Construction
Other Consultant

Other Consultant refers to other organizations which provided significant consultation services for a building project (e.g. wind consultants, environmental consultants, fire and life safety consultants, etc).

Building Monitoring
Siemens Building Technology
Façade

These are firms that consult on the design of a building's façade. May often be referred to as "Cladding," "Envelope," "Exterior Wall," or "Curtain Wall" Consultant, however, for consistency CTBUH uses the term "Façade Consultant" exclusively.

Fire
Siemens Building Technology
Material Supplier

Material Supplier refers to organizations which supplied significant systems/materials for a building project (e.g. elevator suppliers, facade suppliers, etc).

Ceiling
Armstrong World Industries
Façade Maintenance Equipment

About Grand Lisboa

The clear instruction from the client for this project was to create a property that is absolutely original, unlike other recent casino developments in the area which replicate hotels in Las Vegas, USA. Instead the tower is intended to embody the unique vitality and spirit of Macau. The boldly sculpted Grand Lisboa is the antithesis of the “veneered box” template that dominates contemporary casino development. The rich and sensual form of the tower embodies the daring and flamboyant exuberance of modern Macau.

The tower was designed with multi-level long spans of over-hanging floors on two sides of the building to create a lotus leaf-like building form, and an elliptical shaped podium encloses the main gaming floors of the casino. An inspiration for the feathered form of the hotel superstructure was the exotic head dress of a Brazilian show girl’s carnival costume, itself a reflection of the Portuguese influence shared by Macau and South America. The plumes also evoke a blossoming lotus flower, the official emblem of the Macau Special Administrative Region.